toronto clement commons

What's happening with that church condo on Jones?

The Church of St. Clement Riverdale on Jones Ave. was supposed to have been converted into condos by now. In 2012, when the St. Clement's project was announced, the developers set an occupancy date of June 2014, but today there's a big question mark over the site. Literally.

The delay in construction was caused in large part by a change of ownership. The original developer - William Tessler of Sonterlan Corp. - quit the project this summer and two new companies, De Cartier Development Corp. and LifeStyle Real Estate Investments, have since taken over.

"Through numerous miscalculations, whether it was the market, whether it was pricing, timing, the people he had working with him, [Tessler] pulled the plug on the project," says Alex de Cartier of De Cartier Development. "There seemed to be a lot of interest in it, but it didn't fly."

The project, which would have seen the former church converted into condos and a new residential building erected next door, has now been split in two, with De Cartier Development handling the renovation of the church and LifeStyle taking responsibility for delivering the new building.

toronto clement commons

"We basically ripped apart the whole idea," says De Cartier. "The work that [Tessler] had proposed really took a lot of the charm away from the building."

The former Anglican church was built in 1913 in a Gothic Revival style. The congregation began to dwindle in the 1970s and the last religious service was held in 2006. The vacant lot to the south was previously used for coal storage and later a glass workshop, which resulted in soil contamination that had to be rectified. (A digger removed a large gas tank from the ground in the last few weeks.)

De Cartier plans to spend about $5 million converting the church into 16 upscale condos while keeping intact heritage aspects such as the internal gothic arches, pillars, wood paneling, and stained glass windows. "We're showing the owner, 'hey, you are in a church, you are in a 100-year-old building.'"

Next door, Luke Wywrot of LifeStyle is taking on the challenge of putting up the new townhouse building. He says the designs have also changed significantly since 2012. "Before it was more of a condo development, now we're going to have a combination of stacked townhouses and regular townhouses," he says. "We're going for open concept, very modern ... we want to distinguish ourselves from the church."

The 12 townhomes will be built with a small courtyard out front facing Jones Ave., Wywrot says. He hopes to have work complete in late 2015, around the time construction wraps on the church.

The city still needs to approve the proposed changes to both projects, however. "I'm not sure who's going to finish first. It will be a race," Wywrot jokes.

Chris Bateman is a staff writer at blogTO. Follow him on Twitter at @chrisbateman.

Images: Chris Bateman/blogTO


Latest Videos



Latest Videos


Join the conversation Load comments

Latest in City

Doug Ford just got even tougher on Ontario bike lanes with new measures

Toronto's $27 billion Ontario Line just crossed its biggest construction milestone so far

Rare Canadian gold coin sells for over $1.5 million

Toronto ranked among the top 100 best cities in the world for 2025

A full list of all the items included in Canada's holiday GST cut

Liquid soap sold at stores across Canada recalled due to contamination

Canadians to get GST cut on groceries and new $250 rebate ahead of holidays

Snow is finally coming to southern Ontario and here's when it will hit