Leslieville construction

TTC construction fiasco a nightmare for Leslieville

Mention the name "Leslie Barns" to folks in Leslieville and you're libel to get an eye roll. The construction affiliated with the new home for Toronto's low-floor streetcars has been a major downer for neighbourhood businesses and residents, and it just keeps going.

Already well delayed, the latest setback comes in the form of 60 metres of improperly laid streetcar track that will have to be dug up and removed, pushing a construction project that was supposed to be complete last fall into July. The TTC isn't on the hook for the cost of the replacement, as the fault is with the contractor, but that won't appease those who've been anxiously waiting for the work to wrap up.

The section of track in question is located on Leslie street, which lessens the impact on smaller businesses in the area, many of which were impacted by construction on Queen St. last summer. Some day the new streetcar barns will be done, and there might even be functional vehicles to put in them. Some day!


Latest Videos



Latest Videos


Join the conversation Load comments

Latest in City

Canadians can get gift card in Ticketmaster class action and here's who is eligible

Here's what the new Bank of Canada interest rate cut means

2025 declared 'the year of digging' for $27 billion Ontario Line

Here's why one guy kept making Avatar references at Toronto City Hall meeting

Locals impatient about Toronto venue under repair for ages with no end in sight

Lawsuit filed after deaths of Toronto mother and son on trip to Dominican Republic

Controversial Toronto project will make traffic even worse than initially thought

Ontario Child benefit can get parents almost $1,700 per kid every year