toronto construction

A drawn-out construction site screwup is now costing Toronto tens of millions of dollars

Though the people of Toronto are all too familiar with costly construction projects whose completion dates get pushed way past their original schedule, the delays at one work site are particularly infuriating given that they are due to one very simple, but very expensive and time consuming screwup.

While building a new storm sewer under Old Mill Drive, crews managed to tangle a specialized tunnelling machine in some underground wires affixed to a condo building next door, stopping the $3 million piece of equipment dead in its tracks and rendering it completely stuck.

Unfortunately, the solution to the mishap has not been as simple as one might think, and has somehow turned into a nearly two-year-long affair costing $25 million at last estimate, with the anticipated recovery expenses — and time required — continuing to add up.

Earlier in 2023, the City thought it would end up running about $9 million to retrieve the mechanism from underground, which they aimed to do by April.

The timeline was then bumped to the fall, and just this week, to December, with even more holdups expected down the line. Residents in the area were told this month that the schedule is "subject to change" based on underground conditions, weather, and other unforeseen circumstances.

Then there is the work the boring machine was sent down there to do in the first place, which can't be completed until it is, at long last, exhumed.

Those living nearby can now expect the noise and mess of the construction site to continue until at least next spring, which is when final restoration of the street is set to wrap up — that is, if the remote-controlled apparatus can be extracted in time.

Making things worse is the fact that the exorbitant matter, all due to human error, is being paid for by taxpayers when many feel that it should be the responsibility of those at fault, whether that be the subcontractors behind the slipup, the land surveyors for the tunnel or even the developer of the condo whose tiebacks are involved.

Lead photo by

City of Toronto


Latest Videos



Latest Videos


Join the conversation Load comments

Latest in City

Here are all the 2025 statutory holidays in Canada

Huge stretch of TTC subway spanning 11 stations closed for the next 2 weekends

Most people in Toronto now think that the city is moving in the wrong direction

11 million Canada Post parcels now undelivered ahead of Black Friday

Busy Toronto street kicks off major makeover set to wrap in 2025

Here's how much money you could save during Canada's GST holiday

Huge changes planned to 'transform' a major Toronto street

Canadians working in certain fields can expect a big pay bump in 2025